Cory Cannon Civil Litigation Attorney

Construction Litigation

Change Order Dispute Attorney

Unpaid extra work or unapproved charges? Change order claims for Florida contractors and owners. Free consultation.

Updated

Wood roof trusses of a Florida home under construction against a blue sky

Written and reviewed by

Published Updated

A change order is a written amendment to a construction contract that adds, deletes, or revises the work, and adjusts the contract price, the schedule, or both. Nearly every Florida construction contract says a change is not valid unless it is in writing and signed before the extra work begins. Nearly no Florida project actually runs that way. Field conditions shift, the owner says “just take care of it,” the architect issues a sketch instead of a signed form, and the paperwork lags weeks behind the crews. Then the project winds down, the invoices for extras arrive, and one side refuses to honor them.

That is a change order dispute: a contractor or subcontractor carrying real costs for extra work with no signed document behind them, or a property owner holding a bill for “extras” they say they never approved. Those facts can support different affirmative claims. An unpaid contractor may pursue payment for authorized extra work. An owner may seek reimbursement or declaratory relief over charges for work that was never approved. We handle those claimant-side disputes across Tampa Bay as part of our construction litigation practice. Cory Cannon was founded by a Florida attorney with a family history in construction for generations, so we read the records the way the job actually ran: directives, daily logs, time-and-material tickets, pay applications, and the emails in between, as well as the contract language.

Findings Summary

  • An unsigned change order does not automatically bar payment. Florida law can enforce an extra-work claim through waiver by course of conduct, oral modification, and quantum meruit when the owner directed the work, accepted it, and behaved as if the deal had changed.
  • The written change order clause matters, and documented conduct may support waiver or another route to relief. Contemporaneous records carry more weight than an after-the-fact account.
  • Lien deadlines run on extras exactly as they run on base-contract work: Notice to Owner within 45 days of first furnishing (§ 713.06), Claim of Lien within 90 days of final furnishing (§ 713.08), and foreclosure within one year of recording (§ 713.22). Miss them and the extra is usually left unsecured.
  • A willfully exaggerated claim of lien is a fraudulent lien under § 713.31. Include disputed extras only where you have a good-faith basis for them.
  • These cases are won on records and lost on deadlines. Directives, daily logs, signed time-and-material tickets, photos, and the history of how earlier extras were paid decide who prevails.

What a Change Order Is, and Why the Signature Line Matters

Construction contracts require written, signed change orders for a practical reason: they force both sides to agree on scope, price, and time before the money is spent. A signed change order answers three questions at once: what changed, what it costs, and how many days it adds. When that document exists, there is usually nothing to litigate.

The disputes live in the gap between the clause and the job site. A typical clause says something like “no claim for extra work shall be allowed unless authorized by a written change order signed by the owner prior to commencement of the work.” Contractors call these written change order requirements; lawyers call them conditions precedent to payment. Owners rely on them to cap their exposure. Contractors run past them because stopping a crew to chase a signature costs more than the paperwork seems worth, until the owner refuses to pay.

Two guardrails before going further, because this page covers one specific fight:

  • If the work was approved (signed change order, executed contract, no dispute about authorization) and the other side simply is not paying, that is a collection problem, not a change order problem. Start with our construction payment dispute page.
  • If the dispute is about what the base contract itself requires (ambiguous scope language, conflicting drawings, allowances, termination), that is a construction contract dispute, and the analysis starts with the four corners of the agreement rather than with an extra-work claim.

How Change Order Disputes Start

The fact patterns repeat. In Florida project records, unsigned-extras disputes almost always trace to one of these:

  • Verbal directives. The owner, the owner’s representative, or the general contractor’s superintendent tells a crew to change something on the spot. The work gets done. The signature never does.
  • Differing site conditions. The slab is thicker than the drawings showed, the soil will not hold compaction, the existing structure hides rot or corroded connections. The work has to change because the building demands it.
  • Design gaps. The plans conflict or omit detail, and someone has to fill the gap in the field. Whether that gap-filling is “extra” or “included” is exactly what the parties end up fighting about.
  • Storm-repair scope growth. Hurricane and water-loss repairs are the worst offenders in this region. A roof or wall gets opened up and the real damage is larger than anyone scoped. More on this below, because the hurricane version of this dispute has its own trap.
  • “We’ll paper it later.” The parties operate on trust for months (extras are directed, performed, invoiced, and paid without signed forms) and the relationship sours on the last few. The history of informal payments becomes the central evidence in the case.

On the owner’s side, the mirror image: a contractor bills “extras” for work the owner believed was in the base scope, prices field directives at figures no one agreed to, or invoices for work the owner never directed at all. The document fight is the same; only the chair changes.

An Unsigned Change Order Does Not Automatically Kill the Claim

This is the point most contractors and most owners get wrong, in opposite directions. Contractors assume the work speaks for itself and payment must follow. Owners assume the contract clause is an absolute shield. Florida law sits in between, and the outcome usually turns on the conduct of the parties, documented carefully.

Waiver by course of conduct

Florida courts have long held that a written contract can be modified by the parties’ later agreement and conduct, even when the contract says it can only be changed in writing. The Florida Supreme Court set the principle out in Professional Insurance Corp. v. Cahill, 90 So. 2d 916 (Fla. 1956): an oral modification can be enforced, despite a clause prohibiting it, where the parties accepted and acted on the change such that refusing to enforce it would work a fraud on one of them. The court reaffirmed in St. Joe Corp. v. McIver, 875 So. 2d 375 (Fla. 2004), that the parties’ subsequent conduct can modify a contract’s terms.

Applied to change orders: when an owner repeatedly directs extra work, watches it performed, and pays earlier unsigned extras without objection, courts can find the owner waived the written change order requirement by course of conduct. The clause remains relevant. A repeated informal practice can prevent selective enforcement against a later invoice handled the same way.

The limits: Okeechobee Resorts

The doctrine has a floor, and owners’ counsel will stand on it. In Okeechobee Resorts, L.L.C. v. E Z Cash Pawn, Inc., 145 So. 3d 989 (Fla. 4th DCA 2014), the Fourth District tightened the test: the party trying to enforce an oral modification against a no-oral-modification clause must show the modification was mutually accepted and acted upon (both parties’ conduct, not one side’s unilateral reliance) and that refusing enforcement would work a fraud, including that additional consideration was provided and accepted for the modification. A contractor’s own belief that a handshake happened is not enough. What carries the day is contemporaneous evidence that the owner knew, directed, accepted, and behaved as if the deal had changed.

Quantum meruit and unjust enrichment

Quantum meruit (Latin for “as much as he deserved”) lets a party recover the reasonable value of work performed outside a contract’s terms. Florida’s leading construction decision on these theories, Commerce Partnership 8098 Ltd. Partnership v. Equity Contracting Co., 695 So. 2d 383 (Fla. 4th DCA 1997), sets out the elements of the unjust enrichment version of the claim: a benefit conferred on the defendant, the defendant’s knowledge of it, acceptance and retention of the benefit, and circumstances making it inequitable to keep the benefit without paying for it.

Two constraints matter in practice. First, quantum meruit generally cannot override an express contract covering the same work, which is why the fight over whether the extras were inside or outside the contract scope comes first. Genuinely extra work, outside the contract, is where the doctrine breathes. Second, under Commerce Partnership, a subcontractor suing an owner it has no contract with must also show the owner did not already pay someone (usually the general contractor) for that same work. An owner who paid the GC in full is generally not “unjustly” enriched, even if the sub got nothing. That gap is one reason lien and bond rights matter so much for subs, and why the lien analysis runs in parallel in nearly every contractor-side change order case.

Cardinal change and abandonment

When changes stop being adjustments and start being a different project (dozens or hundreds of directives, scope that bears little resemblance to the bid documents), the law has a further concept. Federal contract law calls it a cardinal change: a change so far beyond the contemplated scope that it breaches the contract itself. Florida courts have addressed the same reality through abandonment: where the parties’ conduct shows they stopped performing under the written contract’s terms, the contractor may recover the reasonable value of all the work rather than being held to the original pricing. These are fact-heavy, record-heavy theories. They are built from change order logs, directive counts, and cost histories, which is exactly the kind of record we know how to assemble and, when the numbers are contested, test against independent estimating. When pricing or causation needs outside validation, we retain independent licensed engineers and estimators; we do not ask a jury to take the contractor’s spreadsheet on faith.

For Contractors and Subcontractors: Collecting on Extra Work

A claim for extra work may survive without a signed change order when the evidence supports it. Lien and contract-notice deadlines continue while the authorization dispute remains unresolved.

The lien clock runs on extras too. Extra work you were directed to perform is part of what you furnished to the project, and Florida’s construction lien statute (Chapter 713) protects it on the same unforgiving schedule as base-contract work. Miss these dates and the lien (often the only leverage that gets an unsigned extra paid) is gone:

Step Deadline Statute
Notice to Owner (required for most lienors without a direct contract with the owner) Within 45 days of first furnishing labor or materials § 713.06, Fla. Stat.
Record the Claim of Lien Within 90 days of final furnishing of labor or materials § 713.08, Fla. Stat.
Serve the Claim of Lien on the owner Before recording or within 15 days after § 713.08(4)(c), Fla. Stat.
File suit to foreclose the lien Within 1 year of recording (can be shortened to 60 days by a Notice of Contest of Lien, or 20 days by an order to show cause) § 713.22 (1-year duration; Notice of Contest); § 713.21(4) (show-cause summons), Fla. Stat.

These deadlines are strict, and how they apply to your dates (especially what counts as “final furnishing” when punch-list and warranty work trail the job) is fact-specific. Run your dates through our construction lien deadline calculator, then confirm them with counsel before relying on any of them. A contractor in direct contract with the owner must also deliver a final payment affidavit at least five days before filing the foreclosure suit (§ 713.06(3)(d)), a prerequisite that quietly kills otherwise valid lien claims. Our construction lien page covers the full sequence.

One caution on lien amounts. Disputed extras belong in a lien only when you have a good-faith basis for them. A willfully exaggerated claim of lien is a fraudulent lien under § 713.31, Fla. Stat., which can void the lien entirely and expose you to damages. A supported disagreement over value may be treated differently. The documentation determines where the claim falls.

Prompt payment interest. On private projects, Florida’s prompt payment statute (§ 715.12, Fla. Stat.) adds interest once a proper payment request goes unpaid past the contractual or statutory window. It applies to amounts due under the contract, which loops back to the authorization fight, but it adds real pressure once entitlement is established.

What we actually do. We reconstruct the extras record: every directive, RFI, sketch revision, daily log entry, T&M ticket, and photo, mapped against the pay application history. We price the claim from your job cost records, not from a round number. We preserve lien and, where they exist, bond rights while the authorization fight plays out. And we watch the lien waivers you are asked to sign at each pay application, because a broadly worded waiver can release the very extras you are fighting for. See our answer to “Should I sign a lien waiver?” before you sign the next one.

For Owners: When the Bill Outgrows the Contract

Owners face the reverse problem: a project that was bid at one number and invoiced at another, with the difference labeled “extras.” Some of those charges are legitimate. Some are base-scope work rebilled a second time. Some were never directed by anyone with authority to direct them.

An owner’s affirmative challenge starts with the contract: the written change order clause, who had authority to approve changes, whether notice requirements for claims were followed, and whether the “extra” was actually within the scope the contractor already agreed to build for the contract price. We check the claimed extras line by line against the drawings, the specifications, the pay application history, and reliable pricing evidence. That is the same document-focused analysis we bring to contract disputes generally.

There is an important limit on an owner’s claim. If you or your representative directed the work, watched it go in, and accepted the benefit of it, Florida’s waiver and quantum meruit doctrines described above can apply even without your signature on a form. Strong owner claims usually include a written objection made when the unapproved work or invoice appeared. If the contractor who billed you was not properly licensed, the analysis changes substantially; our guide to suing a contractor in Florida maps the options.

Hurricane Repairs and Scope Creep

Tampa Bay’s storm seasons generate a disproportionate share of these disputes. After events like Hurricane Ian in 2022 and Hurricane Milton in 2024, repair contracts were signed fast, often from insurance estimates rather than full scopes. Then the roof deck came off, or the drywall came down, and the hidden damage (rotted sheathing, corroded fasteners, saturated insulation, code-required upgrades) turned a $60,000 scope into something much larger. Crews kept working because drying a structure cannot wait for paperwork. The signed change orders never caught up.

The legal analysis is the same as above, and the record is often better than the parties realize. Mitigation photos, moisture logs, adjuster correspondence, and supplement requests may document exactly when the scope grew and who knew it. We use that record to build the client’s affirmative claim.

One routing note: if the extra scope exists because the insurance estimate missed it, the real dispute may not be between owner and contractor at all. It may be with the carrier that is refusing to pay for the supplemental work. That is a different fight, against a different opponent, on different deadlines. Our property insurance claims practice handles it, and getting the carrier dispute moving often defuses the change order dispute entirely.

The Paper Trail Checklist: What Wins Change Order Disputes

Whether you are a contractor pursuing payment for extras or an owner seeking relief from unapproved charges, the same documents decide these cases. Build the file in real time:

  • The contract’s changes clause: know who has authority to approve changes and what form approval must take.
  • A written confirmation of every directive. A same-day email or text works: “Confirming your direction this morning to [describe work]. We will proceed on a time-and-material basis and submit a change order for signature.” Silence in response to that message is powerful evidence later.
  • A running change order log: number every potential change, note the date directed, by whom, status (proposed / directed / signed / disputed), and dollar value.
  • Daily logs and dated photos: before, during, and after the changed work, tied to the log number.
  • Signed T&M tickets: get the superintendent’s or owner’s representative’s signature on daily time-and-material tickets even when the change order itself is unsigned. Courts treat a signed ticket as acceptance of the work, if not always the price.
  • Job cost records segregated by change: labor hours, equipment, and material invoices coded to each extra, so the claim is priced from records rather than estimated backward.
  • Written objections. For owners: object in writing the day unapproved work or an unapproved invoice appears. Course-of-conduct waiver is built on silence.
  • Careful lien waivers: exclude disputed extras and pending change orders by name from every partial waiver you sign.
  • Your lien dates: track first furnishing and expected final furnishing from day one; the lien deadline calculator takes thirty seconds and the deadlines take no prisoners.

Change Orders vs. Delay Claims

Extra work almost always consumes extra time, and the two claims are commonly asserted together, but they are analyzed differently. A change order dispute is about entitlement to payment for changed scope. A delay claim is about compensation for lost time: extended general conditions, idle equipment, acceleration costs, or an owner’s liquidated damages assessment. If your dispute includes time impacts, no-damages-for-delay clauses, or schedule analysis, read our construction delay claim page alongside this one; the two claims are often pursued or defended in the same case, but built on separate records.

Fees, and How We Handle These Cases

Change order litigation frequently carries prevailing-party attorney’s fees: by contract, since most construction agreements include a fee clause, and by statute in lien foreclosure actions under § 713.29, Florida Statutes. Fee-shifting cuts both ways: it can make a well-documented claim substantially more valuable, and it makes a weak claim genuinely dangerous to file. We tell clients which side of that line their records put them on before suit is filed, not after. Our FAQ on who pays attorney fees in construction cases covers the mechanics.

For contractor-side extras and collection work, the engagement may be hourly or on staged flat fees, with fee-shifting pursued against the other side where the contract or statute allows. For owner-side disputes, structure depends on the posture of the case. Either way, the engagement starts the same place: a review of the contract, the change order log, and the correspondence, and a candid assessment of what the paper supports. The initial consultation is free.

Talk to a Change Order Dispute Attorney

Change order disputes are won on records and lost on deadlines. If you are holding unpaid extras, or holding an invoice for extras you never approved, bring us the contract and the correspondence. We will tell you what the documents support and what clocks are already running. Cory Cannon serves contractors, subcontractors, and property owners throughout Tampa Bay. Contact us for a free consultation, or start with our construction litigation overview to see how this dispute fits the larger picture.

Frequently Asked Questions

Can a contractor get paid for extra work without a signed change order in Florida?

Often, yes. An unsigned change order does not automatically bar the claim. Florida courts recognize that a written change order requirement can be waived by the parties' course of conduct, that contracts can be modified orally when both parties accepted and acted on the change, and that quantum meruit allows recovery of the reasonable value of extra work an owner knowingly accepted. But these theories are evidence-dependent: directives, daily logs, signed time-and-material tickets, photos, and the history of how earlier extras were handled usually decide the case. Lien deadlines under Chapter 713 keep running while the dispute plays out, so protect them early.

Do verbal change orders hold up in Florida?

They can, but the bar is real. Under Florida Supreme Court precedent, an oral modification can be enforced even against a clause requiring written changes, if the modification was mutually accepted and acted upon by both parties, and refusing to enforce it would work a fraud on the party who performed. One side's say-so is not enough; courts look for contemporaneous conduct, such as the owner directing the work, watching it go in, and paying earlier informal extras. A same-day confirming email or text converts a verbal directive into evidence, which is why documentation habits matter more than the label 'verbal.'

Do I have to pay for extras I never approved?

Not automatically. If the contract requires signed change orders and no one with authority approved the work, you have strong defenses, especially for charges that are really base-scope work rebilled as extras. But the defense weakens if you or your representative directed the work or silently accepted its benefit, because waiver and quantum meruit can run against an owner without a signature. The strongest owner position is a written objection made as soon as unapproved work or an unapproved invoice appears, paired with a line-by-line comparison of the claimed extras against the contract scope.

Can I record a construction lien for unpaid change order work?

Generally yes. Extra work furnished to improve the property is lienable under Chapter 713 on the same deadlines as base-contract work: a Notice to Owner within 45 days of first furnishing for most subcontractors and suppliers, a Claim of Lien recorded within 90 days of final furnishing, and a foreclosure suit within one year. Two cautions: include disputed extras only where you have a good-faith basis, because a willfully exaggerated lien is a fraudulent lien under section 713.31; and confirm your specific dates with counsel, since 'final furnishing' disputes are common.

What is a cardinal change in construction?

A cardinal change is a change, or an accumulation of changes, so far beyond the scope the parties originally contemplated that it amounts to a breach of the contract itself, rather than an adjustment under the changes clause. The doctrine comes from federal government contracting; Florida courts reach similar results through abandonment, finding that the parties' conduct shows they stopped performing under the written contract, which can entitle the contractor to the reasonable value of all the work instead of the original contract pricing. These claims are built on change order logs, directive counts, and job cost records.

How long do I have to sue over an unpaid change order in Florida?

It depends on the theory. A breach-of-contract claim on a written construction contract carries a five-year statute of limitations; an oral or implied contract carries four years (section 95.11). But the deadline that usually bites first is the construction lien: the Claim of Lien must be recorded within 90 days of final furnishing, and a foreclosure suit filed within one year of recording. Because the lien clock is shortest and is often your best leverage on an unsigned extra, protect it first and treat the longer contract deadlines as a backstop, not a plan. Confirm every date with counsel, because the trigger dates are fact-specific.

What is the difference between a construction change directive and a change order?

A change order is a written amendment both sides sign, fixing the changed scope, the price, and any added time at or near the time the work is done. A construction change directive (common under AIA-form contracts) is a written instruction the owner or architect issues to make a change immediately, before the parties have agreed on price or time; it keeps the job moving while preserving the contractor's right to be paid the reasonable cost later. If your contract uses directives, follow its notice and pricing procedures closely: a directive is not a blank check, but it is far stronger evidence than a verbal 'just do it.'

Can a subcontractor lien for extra work the general contractor directed?

Generally yes. Extra work a subcontractor is directed to perform and actually furnishes to the property is lienable under Chapter 713 like any other labor or materials, on the same deadlines: a Notice to Owner within 45 days of first furnishing, a Claim of Lien within 90 days of final furnishing, and foreclosure within one year of recording. Two wrinkles matter for subs: the lien attaches to the property, not to the general contractor's promise, so document that the work was actually installed; and if the owner already paid the general contractor in full for that work, an unjust-enrichment claim against the owner may fail even though the lien itself can survive. Preserve the lien and confirm your dates with counsel.

Does a signed time-and-material ticket count as a change order?

Not by itself, but it is strong evidence. A daily time-and-material (T&M) ticket signed by the owner's representative or the superintendent documents that the extra work was performed and accepted, even if the price was never formally agreed. Florida courts often treat a signed ticket as acceptance of the work, which supports waiver and quantum meruit claims, but the signer can still dispute the rate or markup. Get tickets signed daily, tie them to your change order log, and do not assume a signature on the ticket resolves the pricing fight or replaces a signed change order.

Who has authority to approve a change order?

Only the person the contract says can. Most construction contracts name who may authorize changes (often the owner, a designated owner's representative, or the architect) and set the form approval must take. A field superintendent or project manager may lack authority to bind the owner to a price, which is how extras approved by the wrong person turn into disputes. Before performing directed extra work, confirm who holds authority under the contract, and get the directive in writing from that person or promptly confirm it to them in writing. On the owner's side, limiting and documenting who can approve changes is one of the best defenses against surprise 'extras.'

Should I keep working while a change order is disputed?

Usually you have to, but protect yourself while you do. Most contracts require the contractor to continue performing disputed changed work and to pursue the money through the contract's claims procedure rather than stopping the job. Walking off can itself be a breach. The safer path is to proceed under written protest: confirm in writing that you are performing under the owner's direction, reserve your right to be paid, track the costs separately in your job records, and follow the contract's notice deadlines for claims. Stopping work should be a last resort taken only with legal advice, because a wrongful work stoppage can cost more than the disputed extra.

Talk to Cory

I prepare every matter I accept with trial in mind.

Speak directly with Cory Cannon about your situation. The initial consultation is free, and he walks you through the likely path and the fee options before anything begins. Intake calls are answered 24/7; other calls are typically returned within 24 hours, often within the hour on business days.

Contract broken? Payment withheld? Call in the big guns.

Free Consultation

Please provide only a brief summary. Do not send documents unless I request them.